Leven Road Gasworks is an award winning major urban regeneration development which gained planning approval from the London Borough of Tower Hamlets (LBTH) in October 2019.
The hybrid scheme will provide over c.2,800 homes (35% affordable) across the former gasworks site alongside a school and multiple commercial uses.
- Daylight and sunlight assessments to surrounding residential buildings
- Daylight and sunlight assessments including a view of sky calculations
- Daylight and sunlight analysis within the residential accommodation
- Light pollution assessment
- Overshadowing analysis to internal and surrounding amenity areas
- Solar glare assessment
Throughout the project, a range of bespoke design and assessment techniques were used to optimise the scheme ahead of the planning submission. The client was committed to providing high-quality amenity for both existing and future residents, which required extensive work on the daylight design. The resulting scheme secured planning permission and won Planning Permission of the Year at the Planning Awards.

From initial instruction various design stage works were undertaken to highlight the most constrained areas of the scheme and scheme changes were proposed to improve the light levels within the scheme and improve amenity to future residents. These included optimising the massing at master planning stage as well as considering unit layouts, window sizing and balcony arrangement.
Cutbacks were also undertaken to highlight the areas of the massing causing the most significant impacts on the surrounding neighbouring properties. A great deal of consultation with local residents was undertaken, and concerns were taken on board throughout the process to ensure that the scheme delivered what was required, but also met the aspirations of the developer. In fact it was this community consultation alongside the provision of a development with high levels of amenity that led to this scheme winning its award.
When presenting analysis to the Local Authority, ‘Mirror Assessments’ were used to set alternative targets based on schemes in the surrounding context. This BRE recommended method was accepted by the Local Authority, which meant unavoidable deviations from the targets were deemed acceptable and reasonable.

The Atlas Building comprises a 40-storey residential tower alongside a 10-storey commercial building. We worked closely with the architects to develop a scheme that met relevant design standards, provided high-quality homes and carefully managed its impact on the surrounding environment.
- Daylight and sunlight assessments to surrounding residential buildings
- Daylight and sunlight assessments including a view of sky calculations
- Daylight and sunlight analysis within the residential accommodation
- Overshadowing analysis to internal and surrounding amenity areas
- Light pollution assessment
- Solar glare assessment
This process involved optimizing the massing of both buildings as well as feeding into the design of the internal layouts, windows, and balconies. Preparation of a full environmental impact assessment (EIA) was also included.

Merchant Square is formed of six buildings within the Paddington Basin redevelopment. It is one of the highest density developments in central London and so the provision of good levels of natural lighting, in accordance with relevant design standards, was one of the major challenges of the design.
Because there are large residential buildings in such close proximity to one another, the provision of good levels of natural lighting was greatly dependent upon the collaboration between the different members of the design team.
- Daylight and sunlight assessments to surrounding residential buildings
- Daylight and sunlight assessments including a view of sky calculations
- Daylight and sunlight analysis within the residential accommodation
- Light pollution assessment
- Overshadowing analysis to internal and surrounding amenity areas
- Solar glare assessment
Significant design steering on the massing, facade and internal design was required to ensure a good level of natural lighting and achieve compliance with relevant design standards whilst working within the constraints imposed by many other factors of the design.
The planning application was accompanied by a full environmental statement for which we prepared the daylight, sunlight, overshadowing, light pollution and solar glare chapter. This scheme has subsequently gained full planning permission and is currently under construction.

Royal Wharf is a 41-acre site with 3,385 residential units provided within more than 30 separate blocks. We have so far been involved with the outline master plan application for the full development site and the detailed submission for phases 1 and 2.
- Daylight and sunlight design steering
- Massing layouts and sizing (envelopes & orientation)
- Internal daylight and sunlight design using facade studies
- Window and room sizing
The master planning phase involved an iterative design steering process to ensure an excellent provision of natural lighting was achievable within the blocks whilst still achieving the required volume of development. This process involved the production of highly visual and intuitive analyses, including VSC and APSH façade studies and massing envelopes.
The detailed design of the subsequent phases were informed by our detailed daylight and sunlight calculations and design advice. The planning application was supported by a full environmental statement.

The Residence, now under construction by Bellway Homes, is a significant addition to the Nine Elms Regeneration – a significant new residential, cultural, and business quarter focused around the new American Embassy between Vauxhall and Battersea. The project delivers 510 new homes across two landmark buildings by leading practices Grid Architects and Maccreanor Lavington
- Rights of Light Advice and Mitigation / Management Strategy
- Daylight and sunlight assessments to surrounding residential buildings
- Daylight and sunlight assessments (including view of sky calculations)
- Advanced daylight facade modelling to proposed neighbouring developments
- Daylight and sunlight analysis within the residential accommodation
- Overshadowing analysis to internal and surrounding amenity areas
eb7 were involved from the early phases of the design process managing rights of light risks and working closely with the architects to ensure an appropriate massing response given the changing urban context as well as optimising amenity within the units.

“The Appleton” is the first phase of a larger scheme, close to West Ealing Crossrail station. The scheme is named after a famous building on the Broadway in New York City and references Ealing’s historical origin as an orchard.
The site presented an exceptional opportunity for development whilst posing challenges due to the town centre location and close proximity of neighbouring properties.
- Daylight and sunlight assessments to surrounding residential buildings
- Daylight and sunlight analysis within the residential accommodation
- Overshadowing analysis to internal and surrounding amenity areas
eb7 were involved from the early phases of the design process managing planning risks and working to maximise massing whilst working to an exceptionally tight planning timeframe. Engaging closely with the Local Authority and key stakeholders was key in securing detailed consent only 8 months after our client acquired the site.

This landmark 62-storey 225 metre apartment building in Canary Wharf has delivered 636 apartments, gym and pool facilities as well as residents’ amenity areas, restaurants, cafe and retail units at ground level.
- Daylight and sunlight assessments to surrounding residential buildings
- Daylight and sunlight assessments including a view of sky calculations
- Daylight and sunlight analysis within the residential accommodation
- Light pollution assessment
- Overshadowing analysis to internal and surrounding amenity areas
- Solar glare assessment
eb7 worked alongside Canary Wharf group from the early design stage to deliver a tower of significant scale which causes little impact to its neighbour’s daylight and sunlight amenity.

The new headquarters for TJX Europe is located on Clarendon Road in Watford, opposite Watford Junction station. The development includes a new 12-storey building with three basement levels and refurbishment works to an existing office building on the opposite side of Clarendon Road with link bridge connecting the two buildings. It accommodates around 3,000 employees and serves as TJX UK’s primary head office and campus.
- Daylight and sunlight assessments to neighbouring buildings
- Rights of light assessment for neighbouring buildings and mitigation strategy
- Boundary report with early strategic advice on neighbourly considerations
- Party Wall Act Awards
- Schedules of Conditions
eb7 provided early-stage advice on daylight and sunlight, rights of light, party wall matters and wider neighbourly considerations to ensure any risks were managed through the detailed design. The team helped secure planning permission with a daylight and sunlight assessment and then secured phased Party Wall Awards and access agreements to facilitate delivery of the project. A further 20 schedules of condition were prepared for properties outside the scope of the Party Wall Act to help safeguard against claims for damage.

Director and Party Wall lead Bruce Gawen acted as named surveyor for the redevelopment of the Odeon Cinema on the south western corner of Leicester Square.
- Service of Party wall Notices
- Detailed Schedules of Condition within adjoining properties
- Agreement and service of Party Wall Awards to authorise notifiable works
The project involved the demolition of the existing buildings and top-down construction of a new cinema and hotel complex, comprising of six basement levels, valued at £100 million. Challenges included the site adjoining the listed Westminster Reference Library, which still relied upon subterranean structures from its original construction in the late 17th century. During the course of construction major redevelopment was also being undertaken at the neighbouring Communication House. Innovative engineering solutions and highly sensitive monitoring regimes were put in place in order to mitigate damages risks throughout construction.

The Farmiloe Building is Grade II listed and owned, until recently, by the same family since the 1860’s then used as a glass works. The proposed development includes adaptation of the original building for office use (B1) whilst restoring and retaining the original features, along with the construction of a new sister office building on adjacent land.
- Boundary Report
- Service of Party wall Notices
- Detailed Schedules of Condition within the adjoining properties
- Agreement and service of Party Wall Awards to authorise notifiable works
eb7 reviewed the technical requirements and identified that the demolition works and installation of piled retaining walls were notifiable under the Party Wall etc. Act 1996. The constrained site is located within a designated area of special character in the London Borough of Islington. We therefore worked closely with the project team—particularly the demolition contractor and project engineer—to assess risks to adjoining structures and ensure that the proposed methods were sensitive to the site, its surroundings and neighbouring interests.